Contingency Analysis of the Electricity Transmission Network of Uganda.

Date
2023
Authors
Cadribo, Praise
Journal Title
Journal ISSN
Volume Title
Publisher
Makerere University
Abstract
The operation of the Ugandan Grid is based on the Single outage Contingency criterion. Contingency is the failure of any power system equipment. Contingency analysis is the study of the outage of the components. Uganda’s transmission network has not met the n-1 contingency criterion as evidenced by the blackouts following the failure of some lines mainly due to faults and vandalism. The main aim of the project was to assess the impacts of the failure of the most critical transmission lines on the branch power flows and voltage performance of the network and provide recommendations for long-term planning of the network. The case study was the whole Transmission Network of Uganda and the network data was collected from Uganda Electricity Transmission Company Limited (UETCL). The network was modeled in DigSILENT Power Factory software 15.1 and load flow analysis and contingency analysis were performed to identify the most critical lines to the operation of the grid and the impacts of failure of these extremely important lines were determined. From the analysis of the results, the most critical transmission lines to the operation of the network are 220kV Kawanda-Masaka lines, 220kV Bujagali-Kawanda lines, 132kV Owen Falls-Lugogo lines, and 132kV Owen Falls-Mukono North line. For secure operation of the Western wing of the network, we recommend the proposed construction of the 132kV Kapeeka-Kiboga Mubende-Nkonge line or the proposed 220kV Kafu-Kinyara-Hoima line. Also, we recommend that the single circuit lines in the central region should be upgraded to double circuit lines because most of the load n the network is in the central region and is ever-growing. With Karuma HPP, 400kV Karuma-Kawanda link, and the shunt reactor at Opuyo substation all on, the operation of the Northern and Eastern parts of the network is secure and stable. Operating Karuma at full capacity significantly reduces the loading of some lines and helps improve the bus voltages. Also, when operated at full capacity, Karuma HPP in combination with 1 or 2 other generators can reliably supply the whole country.
Description
A research report submitted to the College of Engineering Design and Art in partial fulfillment of the requirement for the award of the degree Bachelor of Science Electrical Engineering of Makerere University.
Keywords
Contingency Analysis, Electricity Transmission Network
Citation
Cadribo, Praise. (2023). Contingency Analysis of the Electricity Transmission Network of Uganda. (Unpublished undergraduate dissertation) Makerere University; Kampala, Uganda.